Getting Utility Warehouse ready for half-hourly settlement
How I led business analysis at Utility Warehouse for Market-wide Half-Hourly Settlement (MHHS), the biggest change to the UK energy market since the 1990s, and took the business through qualification and migration planning.
- My role
- Lead Business Analyst
- Organisation
- Utility Warehouse, UK energy supplier
- Scope
- 1M+ metering points
- Period
- Sep 2023 – Jan 2026
Results
- Passed MHHS qualification, approved by Elexon, with a traceability matrix showing how 170+ requirements were met.
- 100% of the energy portfolio moved to a new data service provider with zero disruption.
- Migration plan fitted to industry capacity, with the first meters to move identified across a portfolio of 1M+ metering points.
- 130K metering points cleansed with the operational teams, out of 1M+, so migration could start.
MHHS in brief
What it changes
In Great Britain, most household electricity has been settled on estimates. Each supplier’s share of the wholesale market was worked out from standard consumption profiles, then corrected over 14 months as actual meter reads came in.
MHHS settles every meter on its actual half-hourly consumption, using smart meter data, and shortens final reconciliation from 14 months to 4. Ofgem, the GB regulator, decided in April 2021 to move the whole market, and estimated net benefits for consumers of £1.6bn to £4.5bn between 2021 and 2045. Elexon runs the program. Suppliers, data services and meter operators must each pass qualification testing before they can move their meters across.
Why it matters
When settlement uses actual half-hourly data, suppliers pay the real cost of when their customers use electricity. That gives them a reason to offer time-of-use tariffs and to support EV charging, batteries and flexible demand, which the UK needs for net zero. It also changes every supplier’s CRM, billing, metering data and settlement processes at once.
The Australian parallel
Australia has made the same kind of shift. The National Electricity Market moved to five-minute settlement on 1 October 2021, so settlement now matches five-minute dispatch. Western Australia’s reformed Wholesale Electricity Market went live on 1 October 2023.
In WA, Western Power’s rollout of 1.2 million advanced meters gives retailers such as Synergy half-hourly interval data, the same foundation MHHS is built on. The work is familiar: interval data flowing through retail billing and settlement, tariffs built on that data, and market participants proving they’re ready before go-live.
Sources: Ofgem MHHS decision and full business case, Elexon qualification, AEMO five-minute settlement, AEMO WEM reform, WA advanced metering.
How it came together
-
Need
MHHS needed changes to Utility Warehouse’s CRM, billing and settlement processes across 1M+ metering points. Billing runs on Gentrack, which energy retailers across Australia and New Zealand also use.
I facilitated workshops with the C-suite, directors and cross-functional teams on the regulatory impact and on future-state processes.
-
Requirements
- Built and maintained the program’s requirements traceability matrix, tracing 170+ requirements to solution and architecture design, provider documentation, acceptance criteria, 50+ test cases and UAT evidence.
- Documented requirements and customer journeys in BPMN 2.0.
- Led end-to-end delivery of the MHHS platform workstream, coordinating commercial, regulatory and technical teams.
-
Qualification
- Completed the qualification documentation, using the traceability matrix to show how each of the 170+ requirements was met.
- Utility Warehouse passed qualification, with approval from Elexon.
-
Migration planning
- Identified which meters (MPANs) in the portfolio to move first.
- Cleansed the data for 130K of the 1M+ MPANs with the operational teams. Migration couldn’t start until this was done.
- Fitted the migration into a capacity envelope aligned with program capacity across the industry.
- Moved 100% of the energy portfolio to a new data service provider with zero disruption.
Key decisions
- Build in house, or change platform The hardest question was whether to build the MHHS software in house. Halfway through the program, Utility Warehouse changed its billing platform, which took time.
- Prove every requirement Traced each of the 170+ requirements through design, testing and UAT evidence, so qualification could show exactly how each one was met.
- Clean the data before moving it Migration couldn’t start until the data was clean, so we cleansed 130K MPANs with the operational teams first.
- Plan within the industry’s capacity Chose which meters to move first, and fitted the migration into a capacity envelope that matched program capacity across the industry.